264 St. George Street - Demolition in Progress

BELOW:  These first few photos show the carriage houses prior to the start of construction. 

BELOW:  The following photos show demolition well underway.   As of Nov. 11th, all plumbing, electrical, and gas lines

have been shut off.  The electrical service wire is off of the house.  The beams for the garage framing were delivered today.

At 600 lbs per beam, they took all hands on deck to get to the back of the property. 

BELOW:  As of Nov. 17th, the front wall of the old carriage house has been removed and

the middle roof section has been removed.  We have also braced up along the front to support

the buildings while the masonry work gets underway.  

 

BELOW:  The large structural beams called for in the plans have been installed on both sides.  These beams

were heavy.   Each of the four beams weighed in at over 600 lbs.  It took 6 men to carry from the front curb

to the rear of the house.  They are braced temporarily while masonry work is underway.